Korea Rooftop Solar Installation Payback Calculator

Estimate rooftop solar capacity from usable area, value self-consumed electricity and confirmed surplus sales, and model project cash flow, payback, and NPV in KRW.

Input note: Area, generation, and cost defaults are editable planning examples. Replace them with a roof layout, 12-month load data, EPC quotes, and contracted prices.

1. Roof and generation

Estimate capacity after allowing for access paths, obstructions, setbacks, and layout spacing.

Use measured or drawing-based horizontal roof area.

%

Exclude access, fire paths, rooftop plant, setbacks, and shade.

㎡/kW

7.7 starts from the Korea Energy Agency reference of about 23 m² for 3 kW.

kWh/kW·yr

1,272 is a simple annualization of the 14.52% national average utilization shown for 2026 Q1.

2. Electricity use and value

Separate the energy-related portion of the last 12 months of bills that on-site generation can actually avoid.

kWh
KRW

Exclude fixed demand, basic, and non-avoidable charges.

%

Prefer an interval-data overlap of load and generation.

KRW/kWh

Keep zero without a contract. Published SMP is not assumed to be your received price.

3. Investment and operating cost

Align VAT, racking, electrical work, structural scope, and grid connection across quotes.

KRW
KRW
KRW
KRW

Enter approved or contracted support, not an expected application amount.

KRW/year
year
KRW

It is ignored when the replacement year is outside the horizon.

4. Long-term economics

Edit degradation, price and cost escalation, discounting, and generation uncertainty.

%

0.5% is a planning example based on an NREL literature median.

%/yr
%/yr
%/yr
years
%
±%

Rooftop layout plan

29.22 kW

25-year analysis

Net investment

KRW 50,000,000

First-year net benefit

KRW 3,302,727

Nominal cash-flow payback

18.56 years

25-year NPV

-KRW 7,258,889

First-year simple payback

15.14 years

Discounted payback

Not recovered in horizon

Capacity and electricity value

Usable roof area

225 ㎡

First-year generation

37,169 kWh

Self-consumed generation

26,018 kWh

70%

Surplus generation

11,151 kWh

Sale revenue KRW 0

Effective avoided electricity price

150 KRW/kWh

Derived from entered annual use and avoidable charge

Net investment per kW

KRW 1,711,111

First-year cash flow and long-term result

Self-consumption savings

KRW 3,902,727

First-year O&M cost

KRW 600,000

25-year nominal net benefit

KRW 16,714,274

Nominal ROI

33.4%

Lifetime generation in horizon

875,547 kWh

Gross project cost

KRW 50,000,000

Confirmed support KRW 0

Generation sensitivity

A simple planning band of ±15% on specific yield, not a P50 or P90 probability estimate.

Rooftop solar economics by generation sensitivity
ScenarioYear-one generationYear-one net benefitSimple paybackNominal paybackDiscounted paybackNPV
Low31,594 kWhKRW 2,717,31818.4 years23.53 yearsNot recovered in horizon-KRW 15,962,808
Base37,169 kWhKRW 3,302,72715.14 years18.56 yearsNot recovered in horizon-KRW 7,258,889
High42,744 kWhKRW 3,888,13612.86 years15.41 years23.74 yearsKRW 1,445,031

Cash-flow milestones

Rooftop solar generation and cumulative cash flow by milestone year
YearGenerationSelf-use savingsSale revenueO&MInverterNet cash flowNominal cumulativeDiscounted cumulative
Year 137,169 kWhKRW 3,902,727KRW 0KRW 600,000KRW 0KRW 3,302,727-KRW 46,697,273-KRW 46,824,301
Year 536,431 kWhKRW 3,825,256KRW 0KRW 649,459KRW 0KRW 3,175,797-KRW 33,802,951-KRW 35,567,650
Year 1035,529 kWhKRW 3,730,576KRW 0KRW 717,056KRW 0KRW 3,013,521-KRW 18,409,067-KRW 24,292,847
Year 1235,175 kWhKRW 3,693,364KRW 0KRW 746,025KRW 6,000,000-KRW 3,052,661-KRW 18,481,201-KRW 24,263,437
Year 1534,650 kWhKRW 3,638,240KRW 0KRW 791,687KRW 0KRW 2,846,553-KRW 9,840,338-KRW 19,269,468
Year 2033,792 kWhKRW 3,548,189KRW 0KRW 874,087KRW 0KRW 2,674,102KRW 3,877,434-KRW 12,480,864
Year 2532,956 kWhKRW 3,460,367KRW 0KRW 965,062KRW 0KRW 2,495,304KRW 16,714,274-KRW 7,258,889

Interpretation caution

This tool does not decide structural safety, waterproofing, fire safety, electrical safety, grid access, permits, or trading eligibility. Confirm licensing, work-plan, and pre-use inspection requirements with the relevant Korean authorities, KEPCO, safety bodies, and qualified contractors.

Official context checked 2026-07-28 · actual contracts and engineering documents take priority.

The 7.7 m²/kW, 1,272 kWh/kW-year, 0.5% degradation, and sample costs are starting inputs—not statutory values, official quotes, or generation or return guarantees.

Related calculators

What does this rooftop solar payback calculator model?

A rooftop solar decision cannot be reduced to a module price.
Usable roof area, daytime building load, structural reinforcement, waterproofing, grid work, maintenance, and inverter replacement all affect the recovery period.
This calculator first converts roof area into a planning capacity, then links self-consumed generation and confirmed surplus-sale revenue to a year-by-year cash flow.

Results include first-year simple payback, cumulative nominal payback, discounted payback, net present value, and nominal ROI.
A low, base, and high generation comparison makes the estimate useful for challenging an optimistic quote instead of presenting one result as a guarantee.

Factory or warehouse owner

Connect a broad roof and daytime production load to the economics of on-site self-consumption.

Retail or office facility manager

Use actual annual consumption and avoidable energy charges to estimate electricity savings.

Multi-family building manager

Screen a common-area load and roof before commissioning a detailed engineering study.

EPC quote reviewer

Compare structural, grid, support, maintenance, and replacement scope on one basis.

How this differs from a small residential solar ROI estimate

MowaTool already has a residential solar-panel ROI page focused on small home systems and household electricity savings.
This page serves a separate Korea rooftop-building decision: derive capacity from roof area, value daytime self-consumption, align a complete project quote, and include long-term operating cash flow.
It deliberately refuses to award an automatic subsidy or assume that a published market price is the amount the user can receive.

Scope of the rooftop solar payback model and evidence required
Decision areaCalculator treatmentPreferred evidence
System sizeRoof area, usable share, and square metres per kWStamped or surveyed roof layout and module sheet
Electricity valueSelf-consumption and surplus are separatedInterval load, bills, and a sale agreement
Investment scopeEPC, structural, waterproofing, design, and grid costsCash quotes with aligned VAT and exclusions
Long-term costO&M escalation and one inverter replacementService terms and product warranties
EconomicsSimple, nominal, discounted payback, NPV, and sensitivityInternal horizon and discount-rate policy

Korea-specific 2026 context

Jurisdiction note

This English page models a project in South Korea in KRW.
It is a planning tool, not a determination of a generation-business licence, electrical filing or inspection, grid availability, subsidy award, REC status, tax result, or contract entitlement.
The legal and official-source context below was checked on July 28, 2026, and must be rechecked when a project proceeds.

The Korea Energy Agency Green Home page describes a grid-connected solar home and says that a supported system of up to 3 kW needs about 23 m².
Dividing those figures gives about 7.6667 m²/kW, so the editable starting input is rounded to 7.7 m²/kW.
That is not a commercial-roof code rule: module efficiency, row spacing, tilt, fire and maintenance access, parapets, mechanical plant, shade, and structural design can change the layout materially.

The Korea Energy Agency RECloud platform displayed a 14.52% national average utilization rate for reporting-filtered RPS solar facilities for 2026 Q1.
A simple annualization is 14.52% × 8,760 hours = 1,271.952 kWh/kW-year, rounded to the editable 1,272 default.
A first-quarter national average is not an annual yield warranty for a site, so a long-term irradiance study, shading model, EPC production report, or twelve months of measured generation takes priority.

Official and research reference inputs and their limitations
ReferenceObserved valueStarting inputRequired replacement evidence
KEA residential solar area3 kW, about 23 m²7.7 m²/kWActual module and access layout
KEA RPS solar utilization14.52%1,272 kWh/kW-yearSite study or measured production
NREL degradation review0.5%/year median0.5%/yearQuoted module warranty and model
KPX monthly SMPVariable during 2026Not auto-appliedActual eligibility, contract, and settlement price

Why support and sale prices remain manual

Article 27 of the Act on the Promotion of the Development, Use and Diffusion of New and Renewable Energy, current MST 268793 and effective February 1, 2026, provides a basis for diffusion and support projects.
It does not guarantee that a particular building is selected or establish the amount this user will receive.
The Korea Energy Agency also published 2026 recruitment material for residential, building, and balcony-style solar support, but program existence is not an award notice for an individual project.

For that reason, confirmed support defaults to KRW 0 and should change only after an approval or agreement defines the amount.
The same discipline applies to surplus electricity: Korea Power Exchange publishes monthly SMP statistics, but market statistics, REC value, intermediary terms, settlement deductions, and the cash price received by a specific facility are not interchangeable.
Keep the sale-price input at zero until a lawful contract or settlement statement supports another value.

Published SMP is a reference, not automatic project revenue

The KPX monthly page showed integrated SMP values of KRW 103.53, 108.52, 109.99, 118.92, 121.32, and 114.10 per kWh for January through June 2026.
EPSIS describes weighted-average SMP as statistical information for market-price trend analysis.
The calculator preserves those facts in its documentation but does not insert their average into a user contract.

How the calculation flows

1. Convert roof area to installable capacity

Usable roof area equals gross roof area multiplied by the usable share.
Installable capacity equals usable area divided by square metres per kW.
A 300 m² roof at 75% usability and 7.7 m²/kW gives 225 m² and about 29.2208 kW before detailed engineering.

2. Split generation between self-consumption and surplus

Year-one generation equals capacity multiplied by annual specific yield.
Self-consumed generation applies the entered share but can never exceed annual building electricity use.
The remainder is surplus; it produces revenue only when a confirmed price is entered.

3. Derive the value of self-consumed electricity

The effective avoided price equals the annual avoidable energy charge divided by annual electricity use.
Fixed basic or demand charges that remain after installation should not inflate this input.
A time-of-use or demand-managed site needs a separate interval analysis because this model uses one annual blended value.

4. Build annual cash flow

Production declines by the entered degradation rate, while avoided electricity value, sale price, and O&M follow their own escalation assumptions.
The inverter replacement cost is deducted once in the chosen year.
Nominal and discounted cumulative cash flow start at negative net investment and add each annual result.

Worked example with the default planning inputs

The default case uses a 300 m² roof, 75% usability, 7.7 m²/kW, and 1,272 kWh/kW-year.
Annual use is 120,000 kWh and the avoidable annual energy charge is KRW 18,000,000, producing an effective value of KRW 150/kWh.
Self-consumption is 70%, surplus sale price is zero, gross project cost is KRW 50,000,000, first-year O&M is KRW 600,000, and a KRW 6,000,000 inverter cost occurs in year 12.
The horizon is 25 years, degradation is 0.5%/year, O&M escalation is 2%/year, and the discount rate is 4%/year.

Default rooftop solar payback worked-example results
OutputDefault resultInterpretation
Installable capacity29.2208 kWA pre-layout planning capacity
Year-one generation37,168.8312 kWhReplace with the site production study
Year-one self-consumption26,018.1818 kWh70% of generation and below annual use
Year-one surplus11,150.6494 kWhDisplayed but valued at zero without a contract
Year-one electricity savingsKRW 3,902,727Self-consumption multiplied by KRW 150/kWh
Year-one net benefitKRW 3,302,727Savings less KRW 600,000 O&M
Simple payback15.1390 yearsNet investment divided by year-one net benefit
Nominal cash-flow payback18.5558 yearsIncludes degradation, O&M, and inverter replacement
Discounted paybackNot recovered in 25 yearsDiscounted cumulative cash flow stays negative
25-year NPV-KRW 7,258,889Negative at the entered 4% discount rate

Why the three payback measures diverge

Simple payback divides net investment by the first-year operating benefit, so it is fast but ignores later degradation, escalation, replacement, and the time value of money.
Nominal cash-flow payback follows each annual cash flow, while discounted payback reduces future cash flow to present value.
In this example, a 15.1390-year simple result becomes 18.5558 nominal years and no discounted recovery within 25 years.

Generation sensitivity

The default ±15% band is a user-selected planning range, not a statistical P50 or P90 distribution.
Low generation uses 85% of specific yield, base uses 100%, and high uses 115%, while price, cost, degradation, and discount assumptions remain unchanged.

Default low, base, and high generation sensitivity results
ScenarioYear-one generationYear-one net benefitSimple paybackNominal paybackDiscounted payback25-year NPV
Low 85%31,593.5065 kWhKRW 2,717,31818.4005 years23.5283 yearsNot recovered-KRW 15,962,808
Base 100%37,168.8312 kWhKRW 3,302,72715.1390 years18.5558 yearsNot recovered-KRW 7,258,889
High 115%42,744.1558 kWhKRW 3,888,13612.8596 years15.4053 years23.7361 yearsKRW 1,445,031
  • Check whether the low case still recovers inside the ownership or lease horizon
  • Challenge a proposal when only the high case produces a positive NPV
  • Do not raise generation and self-consumption optimistically at the same time without interval evidence
  • Confirm whether curtailment, outage, soiling, snow, shade, and inverter losses are already in the quoted yield
  • Use the same weather period and loss categories when comparing EPC production reports

Step-by-step use

  1. Define the roof boundary.
    Use drawings and a site visit, then exclude plant, fire and maintenance access, setbacks, and shaded zones through the usable-share input.
  2. Replace the area and yield references.
    Change 7.7 m²/kW and 1,272 kWh/kW-year to the actual module layout and site production report.
  3. Prepare twelve months of load and bills.
    Enter use from the same meter and isolate the energy cost that on-site generation can reduce; refine self-consumption with interval load if available.
  4. Enter sale revenue only from evidence.
    Use a contract or settlement value that matches the trading structure, deductions, and tax basis; otherwise retain zero.
  5. Align total investment scope.
    Add EPC, structural work, waterproofing restoration, design, application, inspection, metering, and grid costs, then subtract only confirmed support.
  6. Stress the long-term result.
    Match degradation and replacement to warranties, set an internal discount rate, and review the low case and discounted payback before the headline simple result.

Practical scenarios

Factory or cold-storage daytime load

Continuous daytime production, refrigeration, or HVAC can support a high self-consumption share.
The annual model still cannot capture demand-charge or time-of-use effects, so final approval should use 15-minute interval data.

Retail site with mismatched operating hours

High annual consumption does not guarantee high self-consumption if much of the load occurs at night or on different days.
Keep surplus value at zero without a contract and examine load shifting or storage separately.

Landlord investment and tenant savings

The financial benefit may accrue to a tenant even when the landlord pays for the system.
Roof rights, meter ownership, bill settlement, revenue sharing, lease term, insurance, and reinstatement belong in the contract before the calculated savings are treated as investor cash flow.

Common-area multi-family load

Verify that lifts, pumps, ventilation, and lighting sit behind the meter intended for solar connection.
Resident approvals, reserve planning, waterproofing responsibility, and defects remain separate from this project cash-flow estimate.

Quote-scope checklist

  • Module and inverter model, DC and AC capacity, and DC-to-AC ratio
  • Structural review, racking, anchoring or non-penetrating method, corrosion, and wind design
  • Protection of existing waterproofing, penetration treatment, leak warranty, and reinstatement
  • Switchgear reinforcement, cabling, protection, meter, interconnection, and grid charges
  • Design, permits, filings, inspection, application service, and VAT inclusion
  • Monitoring and communications, periodic inspection, cleaning, insurance, and safety management
  • Weather dataset, production losses, outage, degradation, and curtailment assumptions
  • Product warranty, workmanship warranty, response time, and financially responsible party
  • Contract remedies for support rejection, grid delay, cost increase, or a failed structural review

Licensing, trading, and electrical-safety boundaries

The Korean Law Information Center OPEN API showed the Electric Utility Act as current MST 283981, effective March 10, 2026.
Article 7 addresses licensing for an electric utility business, and Article 31 distinguishes market trading by generation businesses, self-use electrical installations, priority purchase, and other specified participants.
A system size alone is not enough for this calculator to decide licensing or the lawful route to receive revenue.

The Electrical Safety Management Act appeared as current MST 268805, effective February 1, 2026.
Article 8 addresses approval or reporting of work plans for applicable self-use electrical installations, while Article 9 requires applicable work to pass a pre-use inspection before use.
Confirm the project-specific route with the competent authority, KEPCO, the relevant electrical-safety body, and qualified Korean designers and contractors.

Financial payback never replaces roof, fire, or electrical safety

The model does not test roof loading, wind, corrosion, lightning protection, shock and arc hazards, fire spread, firefighter access, waterproofing, or leak risk.
An older structure, sandwich-panel roof, existing leak, undocumented alteration, or mismatch between drawings and the building requires on-site structural, architectural, electrical, and fire-safety review before economics.

Frequently asked questions

How many kW can fit on a 100 m² roof?

At 75% usability and 7.7 m²/kW, the planning result is about 9.74 kW.
The actual result depends on module efficiency, row spacing, tilt, plant, access, setback, shade, and racking, so the detailed layout controls.

Can every Korean site use 1,272 kWh/kW-year?

No.
It is a simple annualization of the 14.52% national average utilization displayed for 2026 Q1, not a site guarantee or statistical P50 result.
Replace it with a site-specific report or measured generation.

Can I add SMP and REC and enter that as the sale price?

A public market price is not automatically the net price available to a project.
Licensing status, trading or intermediary route, fixed-price terms, REC issuance and weighting, fees, settlement, and tax all matter.
Enter a lawful contract or settlement value; otherwise keep zero.

Should I enter the total amount of my electricity bills?

Usually not.
Including fixed basic or demand charges that remain after installation can overstate self-consumption savings.
Isolate the avoidable energy-related portion and model time-of-use and demand impacts separately when material.

How much support should I enter?

Do not enter a value merely because a program exists or an application is planned.
Building use, ownership, program category, budget, approved participant, and selection outcome can change eligibility and amount.
Use only an approval or agreement that confirms the amount.

Does a negative NPV always mean that installation is wrong?

NPV is a financial result under the entered horizon, discount rate, generation, value, and cost scope.
Missing costs can make it worse, while verified support or contract value can change it.
Waterproofing improvement, carbon goals, or RE100 value are not included automatically, but they also should not be monetized without evidence.

What happens when inverter replacement is after the horizon?

No inverter cost appears inside that analysis horizon.
This does not mean replacement is unnecessary, so align the horizon and replacement year with product warranties, expected service life, and the intended holding period.

Sources and maintenance notes

  • Korean Law Information Center OPEN API: Renewable Energy Act MST 268793 Article 27, Electric Utility Act MST 283981 Articles 7 and 31, and Electrical Safety Management Act MST 268805 Articles 8 and 9
  • Korea Energy Agency Green Home: residential solar up to 3 kW and about 23 m² of installation area
  • Korea Energy Agency RECloud: 14.52% national average solar utilization shown for 2026 Q1
  • Korea Energy Agency New and Renewable Energy Center: 2026 residential, building, and balcony-style solar support notices and FAQs
  • Korea Power Exchange KPX and EPSIS: monthly SMP data and the statistical purpose of weighted-average SMP
  • NREL/JA-5200-51664: 0.5%/year median degradation in the reviewed module and system literature

Official context was checked on July 28, 2026.
Recheck effective law, program notices, market rules, agencies, and official data when a project advances.
Actual contracts, engineering, meter data, and quotes always take priority over the demonstration defaults.

Replace the defaults with your roof and your evidence

Use the defaults to understand the model, then enter a roof layout, twelve months of load and bills, aligned EPC quotes, and confirmed contract values.
A decision that remains credible in the low-generation and discounted-payback views is more useful than a headline return built from unsupported assumptions.