Low range
Overhead 110% · technical fee 20%
KRW 84,151,884
Supply price KRW 76,501,713
Estimate a Korean building regular inspection, detailed inspection, or detailed safety diagnosis fee from statutory person-days, 2026 engineering wages, overhead, technical fees, direct expenses, corrections, and VAT.
Choose the service actually being procured and the total floor area of one building. Each service has a separate statutory person-day table.
One building, 1–1,000,000 m². Values between references are interpolated; outside values are extrapolated.
Attached Table 23 multiplies the base person-days by structure and use factors.
This calculator does not derive a weighted factor for mixed structures.
Confirm the primary use in the building register and statement of work.
Article 62 adjusts the fee for complexity, building age, and prior materials supplied.
Age bands apply factors from 1.00 to 1.20.
This refers to the prior report and field-investigation note CAD files.
Enter -15% for simple through +15% for complex.
Enter the wage applied to statutory person-days and additions documented in the actual statement of work.
Construction division default: KRW 310,884, effective 2026-01-01. Verify the contract-date rate.
Additional engineering effort for analysis, expert advice, and similar tasks.
Quoted travel, vehicles, equipment, helpers, material tests, access works, and report printing.
Planning estimate including selected VAT
KRW 93,335,126
Detailed safety diagnosis · 93 person-days · supply price KRW 84,850,114
Statutory fee range KRW 84,151,884 – KRW 102,852,303
Low range
Overhead 110% · technical fee 20%
KRW 84,151,884
Supply price KRW 76,501,713
Planning estimate
Overhead 115% · technical fee 30%
KRW 93,335,126
Supply price KRW 84,850,114
High range
Overhead 120% · technical fee 40%
KRW 102,852,303
Supply price KRW 93,502,094
Table 22 base
93 days
Fieldwork base
31 days
Structure factor
× 1.00
Use factor
× 1.00
Age factor
× 1.05
Prior-material factor
× 1.00
Complexity factor
× 1.00
Adjusted base days
93 days
Combined correction
× 1.05
The area exactly matches the 10,000 m² reference in Attached Table 22.
MOLIT Notice 2025-470 · rules verified 2026-07-27
A Korean building safety diagnosis is not priced by multiplying floor area by an informal rate per square metre.
MOLIT Notice 2025-470 starts with statutory senior-engineer person-days for the service type and building size, adjusts those days for structure and use, and then adds overhead, a technical fee, direct expenses, fee corrections, and VAT.
Building age, structural complexity, and prior investigation materials can change the final amount even when two buildings have the same floor area.
This calculator reproduces that sequence for a single building under the rules verified on July 27, 2026.
It supports a regular safety inspection, detailed safety inspection, and detailed safety diagnosis, then shows a low, planning, and high estimate so owners and procuring entities can compare itemised proposals on the same basis.
Attached Table 22 references are interpolated or extrapolated.
Structure, use, age, complexity, and prior materials remain separate.
The permitted overhead and technical-fee bands produce three totals.
Articles 55 through 62 of the facility safety implementation guideline define a fixed-estimate approach based on standard staffing.
The calculator’s planning scenario uses the midpoint rates of 115% overhead and 30% technical fee for comparison, while the low and high scenarios preserve the full permitted ranges.
Direct labor = total person-days × senior engineer daily wage.
Overhead = direct labor × 110% to 120%.
Technical fee = (direct labor + overhead) × 20% to 40%.
Supply price = subtotal including direct expenses × combined correction factor.
Total = supply price + selected 10% VAT.
Figures are senior-engineer person-days, with field-investigation days in parentheses.
Detailed inspection and diagnosis references begin at 5,000 m², so a smaller building is extrapolated from the nearest two non-zero points as Article 56 requires.
| Floor area | Regular inspection | Detailed inspection | Detailed diagnosis |
|---|---|---|---|
| 500 m² | 3 (2) | — | — |
| 1,000 m² | 3 (2) | — | — |
| 3,000 m² | 4 (2) | — | — |
| 5,000 m² | 5 (3) | 17 (11) | 85 (26) |
| 10,000 m² | 6 (4) | 18 (12) | 93 (31) |
| 30,000 m² | 10 (7) | 29 (21) | 148 (66) |
| 50,000 m² | 14 (9) | 39 (29) | 205 (102) |
| 100,000 m² | 24 (15) | 65 (50) | 347 (193) |
Interpolated staffing is rounded to one decimal place under Article 56.
The result panel identifies exact, interpolated, below-range extrapolated, and above-range extrapolated cases.
| Group | Building type | Factor |
|---|---|---|
| Structure | Steel frame | 0.80 |
| Structure | Masonry | 0.90 |
| Structure | RC, SRC, or PC | 1.00 |
| Structure | Timber | 1.20 |
| Structure | Special structure | 1.30 |
| Use | Office or retail | 1.00 |
| Use | Residential | 1.10 |
| Use | Special use or stadium | 1.20 |
| Building age | Factor |
|---|---|
| 15 years or less | 1.00 |
| Over 15 through 25 | 1.05 |
| Over 25 through 35 | 1.10 |
| Over 35 through 55 | 1.15 |
| Over 55 years | 1.20 |
Structural complexity may correct the fee from -15% for a simple configuration to +15% for a very complex one.
Supplying either a prior report or field-investigation note CAD files applies 0.97, while supplying both applies 0.95.
Do not select a reduction merely because ordinary drawings exist; confirm that the delivered materials meet the guideline and procurement requirements.
Assume a 20-year-old reinforced-concrete retail building needs a detailed safety diagnosis.
Structure and use factors are both 1.00, no prior materials are supplied, and optional labor and direct expenses remain zero during the initial budget stage.
| Item | Calculation | Amount |
|---|---|---|
| Base person-days | Table 22 at 10,000 m² | 93.0 days |
| Direct labor | 93.0 × KRW 310,884 | KRW 28,912,212 |
| Overhead | Direct labor × 115% | KRW 33,249,044 |
| Technical fee | (Labor + overhead) × 30% | KRW 18,648,377 |
| Uncorrected subtotal | Direct expenses assumed zero | KRW 80,809,633 |
| Age correction | 20 years × 1.05 | KRW 84,850,114 |
| VAT | Supply price × 10% | KRW 8,485,011 |
| Planning total | Supply price + VAT | KRW 93,335,126 |
Article 60 treats work beyond the basic task as optional work when it is needed to achieve the investigation’s purpose.
This is why two legitimate proposals for buildings of the same size can differ substantially without either proposal using the wrong base table.
Measured drawings, structural or geotechnical analysis, and expert advice.
Core sampling, strength or composition tests, drilling, and GPR surveys.
Temporary works, surface cleaning, and removal and restoration of finishes.
Travel, vehicles, assistants, hazard allowance, equipment use, and report printing.
No. Their statutory person-days differ greatly, and a diagnosis may require a broader safety assessment. Select the exact service stated by the authority or procurement document.
The detailed inspection and diagnosis tables begin at 5,000 m². Article 56 requires the nearest two non-zero references when a listed size is unavailable.
Enter the written project quote, not a national-average guess. Include applicable travel, vehicles, assistants, tests, access equipment, temporary works, reinstatement, and report production.
No. It uses midpoint rates within the permitted bands for budgeting. The contract price depends on scope, procurement rules, the firm’s itemisation, and agreed conditions.
Not directly. Article 61 has a cluster-building staffing method based on the largest block and related blocks. Obtain a qualified calculation for a multi-building scope.
No. Only a qualified institution can assess condition and safety after fieldwork and testing. This calculator estimates the service fee, not the outcome.
Do not assume so. KENCA may publish a new annual wage survey. Verify the construction-division senior engineer rate at procurement and replace the editable default.
The calculator reflects rules in force on July 27, 2026.
A later amendment to the Facility Safety Act was listed to take effect on August 28, 2026, so users procuring after that date should recheck the current act and any amended guideline before relying on these assumptions.
Check the building register for floor area, structure, and use, then enter the prior materials and optional-task quantities supported by the proposal.
Saving the three-scenario range and itemised breakdown makes a like-for-like procurement review much easier than comparing headline totals alone.