Korea Building Electrical Capacity Upgrade Cost Calculator

Build a new-equipment load schedule, compare minimum, recommended, and planned contract power, and estimate KEPCO contributions, on-site work, and monthly basic-charge changes.

Start from a fictional upgrade example

Replace every default with a load schedule, recent bill, KEPCO response, and VAT-inclusive like-for-like quotes.

1. Existing and target contract power

Separate current peak and reserve to build minimum, recommended, and planned options.

kW
kW

Whole kW, no lower than existing

kW

Metered demand or conservative coincident peak

%

A pre-design assumption, not an automatic contract ruling

2. KEPCO supply and facility contribution

Calculate the public standard table and optionally override it with a confirmed KEPCO quote.

m

Include base distance; excess under 1 m is discarded

m

Only the published overhead rate is automated

KRW incl. VAT

3. New-equipment load schedule

Apply peak diversity to connected load. Verify equipment data and operating interlocks with an electrical professional.

Equipment 1

kW
units
%

Equipment 2

kW
units
%

Equipment 3

kW
units
%

4. On-site electrical construction quotes

Enter VAT-inclusive payable quotes on the same scope; contingency applies only to on-site work.

KRW
KRW
KRW
KRW
KRW
KRW
%

Not applied to the KEPCO contribution

5. Monthly basic charge

Compare billing demand and optional daytime lagging power factor only; energy charges, VAT, and levies are excluded.

kW

From the latest bill

KRW/kW

KRW 6,160 is a General Service (A) I low-voltage reference

%

Daytime 09:00–23:00

%

Discount is capped at 95%

Total initial planning budget

KRW 1,188,000

Applied KEPCO contribution KRW 1,188,000 + VAT-inclusive on-site budget KRW 0

Monthly basic-charge increase

KRW 92,400

KRW 1,108,800 per year

Capacity planning summary

Added coincident demand

16.7 kW

31 kW connected

Projected peak

46.7 kW

30 + 16.7 kW

Minimum / recommended

47 / 54 kW

15% reserve

Planned capacity margin

+8.3 kW

+1 kW versus recommended

Planned upgrade

15 kW

Automatic KEPCO table

KRW 1,188,000

Including VAT

On-site budget

KRW 0

Entered quotes + contingency

Initial cost per added kW

KRW 79,200

Load calculation detail

Connected and coincident demand by equipment
EquipmentRatedQtyConnectedDiversityCoincident
AC EV chargers7 kW214 kW50%7 kW
Heat pump12 kW112 kW60%7.2 kW
Commercial kitchen equipment5 kW15 kW50%2.5 kW

KEPCO facility contribution

Basic contribution
KRW 1,080,000
0 m new-line excess
KRW 0
0 m added-line excess
KRW 0
Automatic supply amount
KRW 1,080,000
VAT at 10%
KRW 108,000
Automatic total including VAT
KRW 1,188,000
Applied amount
KRW 1,188,000

On-site work and contingency

Service, feeders, and cable
KRW 0
Panels, switchgear, and breakers
KRW 0
Transformer and receiving equipment
KRW 0
Design and supervision
KRW 0
Inspection, testing, and application
KRW 0
Other construction
KRW 0
On-site direct cost
KRW 0
10% contingency
KRW 0
On-site construction budget
KRW 0

Monthly basic charge before and after upgrade

Energy charges, VAT, and the power-industry levy are not included.

Billing demand and power-factor-adjusted basic charge before and after upgrade
CaseBilling demandBefore adjustmentLagging PFAdjustmentFinal basic charge
Before40 kWKRW 246,40090%KRW 0KRW 246,400
After55 kWKRW 338,80090%KRW 0KRW 338,800

Staged upgrade comparison

The KEPCO amount in this table is the automatic public-table value, not the manual quote.

Minimum, recommended, and planned contract-power scenarios
ScenarioContract powerUpgradeAutomatic KEPCOBilling demandMonthly basicChange
Minimum47 kW7 kWKRW 431,20047 kWKRW 289,520KRW 43,120
Recommended54 kW14 kWKRW 1,093,40054 kWKRW 332,640KRW 86,240
Planned55 kW15 kWKRW 1,188,00055 kWKRW 338,800KRW 92,400

Boundaries and next actions

On-site construction quotes are missing

The current total is mainly the KEPCO contribution, not a complete construction budget.

Check conditions outside the standard contribution table

KEPCO design controls mixed supply, special facilities, design-adjustment contributions, and work boundaries.

Confirm design, contractor, and pre-use inspection scope

Registered-contractor work and pre-use inspection or filing requirements must be checked for the actual installation.

Official tables and terms were checked on 2026-08-19. Give this result and load schedule to KEPCO and a registered electrical contractor to confirm supply method, work boundaries, outage planning, design, and pre-use inspection in writing.

Related calculators

KEPCO public tables and Standard Terms checked August 19, 2026

A Korean building power upgrade is not one construction quote

Adding electric-vehicle chargers, a heat pump, commercial kitchen equipment, HVAC, servers, or production machinery can change both the building infrastructure and its continuing electricity bill.
A useful budget separates the required contract-power decision, the facility contribution payable to Korea Electric Power Corporation, the customer-side electrical work, and the monthly basic-charge increase.
This Korea-specific calculator turns an equipment load schedule, a recent bill, and like-for-like contractor quotes into a planning brief for KEPCO and a registered electrical contractor.
It does not design the installation or approve a contract-power application.

Keep three cost boundaries separate

1. KEPCO contribution

The public standard calculation uses added contract power, supply voltage, overhead or underground service, and line distance beyond the published base distance.
A confirmed KEPCO quote takes priority where special or mixed conditions make the standard table incomplete.

2. Customer-side work

This can include service and feeder cables, conduit and excavation, panels and switchgear, a transformer or receiving equipment, design, supervision, testing, applications, outage work, and reinstatement.
Enter payable quotes including Korean VAT on a consistent scope.

3. Monthly basic charge

The comparison applies the user-entered KRW/kW basic-charge rate to contract power or estimated billing demand.
Optional daytime lagging power-factor adjustment is included, but energy charges, VAT, and the power-industry levy are not.

Mixing these boundaries makes omissions and double counting difficult to detect.
A contractor may collect a KEPCO payment as an agent, or the customer may pay KEPCO directly.
A panel or breaker may already be included in an equipment package while another quote lists it again.
Separating the automatic KEPCO table, a manual KEPCO override, customer-side direct costs, contingency, and the continuing fixed charge creates a cleaner procurement comparison.

KEPCO standard facility-contribution rates used here

The values below were read from the KEPCO basic and distance facility-contribution tables on August 19, 2026.
Every published amount in these tables excludes 10% Korean VAT.
Low-voltage single-phase and three-phase service use the same basic-contribution schedule, while their overhead new-line distance rates differ.
KEPCO notes that the high- and extra-high-voltage basic schedule applies where total contract power is at least 100 kW, so a lower target selected with high voltage produces a review warning.

KEPCO basic facility contribution by voltage and service method
Supply categoryFirst 5 kWEach kW above 5Application note
Low voltage, overheadKRW 220,000KRW 86,000Single- or three-phase
Low voltage, undergroundKRW 527,000KRW 123,000Single- or three-phase
High or extra-high voltage, overheadKRW 17,000/kWKRW 17,000/kWCheck the 100 kW total threshold
High or extra-high voltage, undergroundKRW 44,000/kWKRW 44,000/kWCheck the 100 kW total threshold

For a low-voltage upgrade above 5 kW, the calculator adds the fixed first-five-kilowatt amount and then multiplies only the remaining upgrade by the incremental rate.
For high or extra-high voltage, it multiplies every added kilowatt by the applicable overhead or underground rate.
If target contract power equals existing contract power, the automatic facility contribution is zero even if a distance was entered, because there is no calculated upgrade event.

KEPCO distance facility contribution rates and base distances
MethodBase distanceLow single, newLow three-phase, newHigh voltage, newAdded-line distance
Overhead200 mKRW 39,000/mKRW 43,000/mKRW 43,000/mLow KRW 5,000/m; high KRW 10,000/m
Underground50 mKRW 60,000/mKRW 60,000/mKRW 110,000/mNo automated public rate

The calculator subtracts the 200 m overhead or 50 m underground base distance and discards a remaining fraction below one metre.
For example, 205.9 m of overhead new line is charged as five excess metres, not six.
This arithmetic cannot determine KEPCO's service point, reference point, actual route, mixed overhead and underground split, pole work, road work, or special-supply facilities.
Use a confirmed design response for those boundaries.

A disciplined input workflow

  1. Verify existing contract power and current peak.
    Read contract power and, where available, billed demand or maximum demand from recent Korean electricity bills and meter records.
    If no interval or demand record exists, document the conservative operating assumption used for the existing peak.
  2. Build the new-equipment load schedule.
    Enter electrical input kW per unit, quantity, and the share expected to operate at the relevant peak.
    Do not confuse useful heating or cooling output with electrical input.
    Confirm EV load management, heat-pump resistance backup, motor starting, duty cycling, and operating interlocks with the designer or manufacturer.
  3. Compare minimum, recommended, and planned power.
    Minimum power rounds projected peak up to a whole kilowatt.
    Recommended power adds the user's reserve assumption before rounding, while planned power is the target entered for the project.
    These are planning cases, not a KEPCO contract determination.
  4. Select the supply condition and enter confirmed distance information.
    Choose low-voltage single-phase, low-voltage three-phase, or high voltage, then choose overhead or underground service.
    Enter actual line distance including the base distance only after confirming how KEPCO measures it.
  5. Replace the automatic amount when KEPCO has quoted the project.
    Turn on the manual quote and enter the amount payable including VAT.
    The result retains the public-table calculation beside the applied quote so the difference remains visible.
  6. Align customer-side quote scopes.
    Separate cable and route work, panels, receiving equipment, design and supervision, inspection and applications, and other outage or reinstatement work.
    Use VAT-inclusive payable values and apply contingency only to this customer-side subtotal.
  7. Replace the reference basic-charge rate.
    Enter the actual KRW/kW rate for the tariff and option shown on the latest bill.
    Use the demand-meter option only when the customer has a maximum-demand meter, and use the power-factor option only after confirming Article 43 eligibility.

How the load and capacity calculation works

Coincident demand by item

Rated electrical input × quantity × peak diversity percentage ÷ 100 gives each item's coincident demand.
The calculator sums all items and adds that amount to current peak demand.

Capacity cases

Minimum is the ceiling of projected peak.
Recommended is the ceiling of projected peak multiplied by one plus the reserve percentage.
Planned margin is target contract power minus projected peak, so a negative value clearly identifies a deficit.

Default fictional load schedule

  • Two 7 kW AC EV chargers at 50% peak diversity contribute 7.0 kW.
  • One 12 kW heat pump at 60% contributes 7.2 kW.
  • One 5 kW commercial kitchen item at 50% contributes 2.5 kW.

Added coincident demand is 16.7 kW.
Adding the existing 30 kW peak gives a projected peak of 46.7 kW.
Minimum contract power is 47 kW, recommended power at a 15% reserve is 54 kW, and the fictional 55 kW plan has 8.3 kW of margin.

Diversity is not a universal national percentage.
It depends on operating hours, control logic, weather, production sequence, charging policy, and whether loads overlap with the building's existing peak.
Where evidence is weak, run several cases and have the operating assumptions reviewed rather than treating a single default as a rule.

Worked cost example and staged choices

Moving from 40 kW to 55 kW is a 15 kW low-voltage overhead upgrade in the default example.
The basic contribution is KRW 220,000 for the first 5 kW plus ten times KRW 86,000, producing KRW 1,080,000 before VAT.
VAT is KRW 108,000, so the automatic KEPCO total is KRW 1,188,000.
With no excess line distance and no customer-side quote entered, the displayed initial budget is KRW 1,188,000, but that is not a complete construction budget.

Minimum, recommended, and planned upgrade cases in the default example
CaseContract powerAdded powerAutomatic KEPCO incl. VATMonthly basic chargeMeaning
Minimum47 kW7 kWKRW 431,200KRW 289,520Projected peak rounded up
★ Recommended54 kW14 kWKRW 1,093,400KRW 332,640Includes 15% reserve
Planned55 kW15 kWKRW 1,188,000KRW 338,800User-entered target

The monthly figures above use the editable KRW 6,160/kW reference and no power-factor adjustment.
Existing basic charge is 40 × KRW 6,160, or KRW 246,400 per month.
The 55 kW plan is KRW 338,800 per month, an increase of KRW 92,400 per month and KRW 1,108,800 per year before energy charges, VAT, and levies.
KRW 6,160/kW is the General Service (A) I low-voltage basic rate shown on the KEPCO tariff page effective November 9, 2023.
It is a convenient editable example, not a rate that applies to every Korean building.

Billing demand and daytime lagging power factor

Without a demand meter

The comparison uses existing contract power before the upgrade and target contract power after it.
Confirm the actual billing rule and tariff category on the bill and with KEPCO.

With a demand meter

The estimate takes the largest of current billed demand, projected peak rounded up, and 30% of target contract power rounded up.
This preserves known demand history instead of resetting it to zero, but it is still only an Article 68 approximation.

KEPCO Standard Terms Article 68 considers maximum demand from relevant seasonal months, along with contract changes and meter-installation history.
A single recent billed-demand value cannot reproduce the complete monthly rule.
Obtain the relevant demand history when the fixed-charge result materially affects the investment decision.

Current KEPCO daytime lagging power-factor adjustment examples
Lagging power factorAdjustment rateAdjustment on KRW 616,000Adjusted basic charge
85%+1.0%+KRW 6,160KRW 622,160
90%0%KRW 0KRW 616,000
95%-1.0%-KRW 6,160KRW 609,840
100%-1.0%, capped at 95%-KRW 6,160KRW 609,840

Under the current Article 43 rule, daytime lagging power factor below 90% adds 0.2% of the basic charge for each percentage point, assessed down to a 60% floor.
A value above 90% deducts 0.2% per point, capped at 95%.
The calculator deliberately does not use the 0.5% figure found in older material.
The rule applies only to eligible tariff and metering conditions, including specified low-voltage customers at 20 kW or more and relevant high-voltage customers.
Night-time leading power-factor charges from 23:00 to 09:00 require separate reactive-energy information and are excluded.

Application scenarios

EV charging

Determine whether all chargers can operate at full output together and whether a load-management controller limits the site peak.
Do not simply add charger nameplate totals to contract power when an enforceable control strategy changes coincident demand.
Record that control strategy in the design and operating documents.

Heat pumps and electric boilers

Include compressor input, pumps, controls, defrost operation, and any cold-weather resistance backup rather than using thermal output capacity.
Test whether winter heating demand overlaps the building's established demand peak.

Commercial kitchens and HVAC

Check whether induction equipment, ovens, dishwashers, refrigeration, ventilation, and HVAC overlap during preparation or service.
A tenant should also confirm landlord approval, available receiving capacity, work ownership, and reinstatement obligations.

Factories, laboratories, and server rooms

Motor starting, UPS losses, redundancy, cooling, harmonics, and critical-load requirements cannot be designed from steady kW alone.
Use the calculator for a cost envelope, then commission fault-level, protection-coordination, cable, voltage-drop, grounding, and power-quality design.

Quote-normalisation checklist

  • Use the same target contract power, supply voltage, phase, and overhead or underground assumption in every quote.
  • State whether the KEPCO facility contribution is paid directly or included as a pass-through amount handled by the contractor.
  • Mark the start and end of customer-side service and feeder work, cable length, conduit, excavation, fire-stopping, and reinstatement.
  • Separate panels, switchgear, breakers, metering, controls, and modifications to existing equipment.
  • Identify transformer, cubicle, receiving, and protection equipment and the conditions under which existing assets may be reused.
  • Assign design, supervision, drawings, technical review, test reports, KEPCO application, and pre-use inspection responsibilities.
  • Price outage duration, temporary power, business interruption controls, night or holiday work, and occupant notices.
  • Align VAT, removal, disposal, lifting, road or parking reinstatement, provisional sums, and contingency.
  • Record quote validity, commodity escalation, equipment lead time, commissioning, warranty, and exclusions.

Frequently asked questions

Can I submit the recommended result directly as my KEPCO contract power?

No.
Minimum and recommended power are planning results based on the diversity and reserve assumptions entered by the user.
KEPCO contract calculation, the detailed rules, the actual receiving arrangement, and professional electrical design take priority.
Use the result to frame the question, not to replace approval.

What diversity percentage should I use?

There is no universal percentage for every project.
Use manufacturer data, actual meter records, operating schedules, control logic, interlocks, and a documented worst credible overlap.
Compare a conservative case when evidence is weak and ask the designer to verify the operating scenario.

Does zero distance contribution mean no line-work cost?

No.
The line may be within the public base distance or no confirmed distance may have been entered, while customer-side cable, conduit, excavation, road work, reinstatement, or special facilities still cost money.
Confirm the service point and work boundary in KEPCO's response and the contractor's quote.

Is KRW 6,160/kW valid for every building in Korea?

No.
It is the editable General Service (A) I low-voltage reference from the tariff table effective November 9, 2023.
General, industrial, educational, high-voltage option, seasonal, and time-of-use arrangements can have different structures.
Replace it with the rate confirmed on the latest bill or by KEPCO.

Does improving power factor to 100% keep increasing the discount?

No.
The daytime lagging discount in this implementation is capped at 95% under the current Article 43 rule.
Eligibility depends on tariff, contract power, and reactive metering, while excessive correction can create night-time leading-power-factor issues.
Do not size correction capacitors without harmonic and system review.

Can this tool decide whether a pre-use inspection is required?

No.
Electrical Safety Management Act Article 9 and its Enforcement Rule Article 6 must be applied to the actual facility type, capacity, and construction scope.
Inspection fees, testing, drawings, filings, and attendance can also vary.
Enter only a quote confirmed for the actual project.

Why does the staged table ignore my manual KEPCO quote?

A manual quote normally relates to one defined planned scope.
Applying the same amount to minimum and recommended cases would imply that KEPCO quoted those different designs.
The staged table therefore uses the same public automatic formula for all three cases, while the main planned budget applies the manual override.

Legal and technical boundary

  • The calculator does not create a single-line diagram or size transformers, breakers, conductors, grounding, protection, correction capacitors, or harmonic filters.
  • It does not calculate short-circuit current, selectivity, voltage drop, starting performance, fire stopping, resilience, or an outage method.
  • Whether work must be carried out by a registered electrical contractor under Electrical Construction Business Act Article 3 depends on the actual scope and any statutory exception.
  • It does not determine pre-use inspection, filing, electrical safety manager, building approval, fire-code, road-excavation, landlord, or condominium-management requirements.
  • The KEPCO public table does not reproduce every special facility, mixed route, design-adjustment contribution, or allocation of utility and customer work.

Use the output as a transparent cost envelope and question list.
A registered Korean electrical contractor and the appropriate electrical engineer should inspect the existing service, receiving equipment, panels, routes, protection, and operating constraints.
KEPCO should confirm the supply voltage, service point, measured line distance, facility contribution, construction boundary, contract-power method, and tariff consequences in writing.

Official references and maintenance date

The calculation was checked on August 19, 2026 against KEPCO Standard Terms Articles 43, 68, and 93, the public basic facility-contribution table, and the public distance facility-contribution table.
The legal boundary references Electric Utility Act Article 16 effective March 10, 2026; Electrical Safety Management Act Article 9 effective February 1, 2026; its Enforcement Rule Article 6 effective July 1, 2026; Electrical Construction Business Act Article 3 effective November 28, 2025; and the 10% VAT rate under Value-Added Tax Act Article 30 effective January 2, 2026.
Rates and terms can change after the checked date.
Reopen the official pages before relying on the result for procurement or an application.

Turn the result into written project questions

Save the calculation and attach equipment schedules, recent bills, maximum-demand records, and site photographs.
Ask KEPCO to confirm the supply voltage, service point, work boundary, facility contribution, contract-power method, and tariff treatment.
Ask the registered contractor to confirm receiving capacity, cable and panel scope, outage method, design, commissioning, inspection, reinstatement, VAT, exclusions, and warranty.
Comparing minimum, recommended, and planned cases on the same assumptions makes immediate need and future reserve visible without pretending that a planning calculator is an electrical design.