Korea Construction Environmental Budget Allocation & Settlement Checker

Check the minimum indirect environmental budget by work type, contract shortfalls, separate waste costs, double counting and indirect spending settlement ranges under Korean 2026 rules.

1. Reference date, client and work type

With two work types on one site, the type with the larger work amount applies. Calculate separately procured contracts one by one.

2. Contract breakdown amounts

Use the direct construction cost in the client’s cost statement. It is the base for the minimum indirect amount.

The “environmental conservation” line in indirect costs, separate from the safety and health budget.

Leave unknown amounts blank; the related totals stay pending. Enter 0 only for confirmed none. Amounts exclude VAT.

3. Waste separation and double-counting checks

With a public client, 100 tonnes or more must be procured separately.

Guideline Article 5(2): reclassify to the line that matches the main purpose.

4. Indirect spending and settlement status

Settlement follows the quantities and costs confirmed by the client or construction manager at progress or completion inspection. Blank rows count as no spending.

Candidate amount to request after consultation under Guideline Article 9.

5. Review for the client and construction manager

Arithmetic cross-check under Korean 2026 rules. It is not a client settlement approval, contract change, price adjustment or environmental-permit decision, and special contract terms may prevail.

★ Minimum indirect environmental amount

Unknown / pending

Contract shortfall to review

Unknown / pending

Indirect settlement reduction range

Unknown / pending

Applied work type: Pending · Minimum rate pending · Contract indirect / direct cost Unknown / pending · Environmental total / direct cost Unknown / pending

Environmental budget composition, contract amounts and minimum
ItemAmountBasis / note
Direct: dust controlUnknown / pendingClean Air Conservation Act facilities
Direct: noise and vibrationUnknown / pendingNoise and Vibration Control Act facilities
Direct: waste facilitiesUnknown / pendingConstruction Waste and Wastes Control Act facilities
Direct: water pollution controlUnknown / pendingWater Environment and Sewerage Acts
Direct conservation subtotalUnknown / pendingMarket unit prices, standard estimates or quotes (no fixed minimum)
Indirect conservation in contractUnknown / pendingAnnex 8: at least direct cost × minimum rate
Minimum indirect amountUnknown / pending- · rounded up to whole KRW
Environmental conservation totalUnknown / pendingDirect + contract indirect
Waste: on-site handling and recyclingUnknown / pendingAnnex 8 item 2(a)(1),(3)
Waste: construction-waste disposalUnknown / pendingExcluded if procured separately (item 2(c))
Waste: business and designated wasteUnknown / pendingFor example asbestos from demolition
Waste disposal totalUnknown / pendingSeparate line from conservation (direct expenses)
★ Environmental management totalUnknown / pendingOf direct cost Unknown / pending
Duplicate and reclassification review with waste separation duty
Review itemAmountBasis
Main-purpose reclassification0 KRWGuideline Art 5(2)
Double-counted in another line0 KRWPricing rule Art 39 cost lines
Separately procured waste duplicate0 KRWAnnex 8 item 2(c)
Total to review0 KRWConservation after cleanup Unknown / pending · waste Unknown / pending

Separate waste procurement: Pending: client type or tonnage unknown

Indirect environmental spending and settlement status
Indirect lineSpentStatus
Testing and measurement (dust, noise, water)0 KRWConfirmed
Inspections0 KRWConfirmed
Education, guidance and training0 KRWConfirmed
Permits and filings (dust, specified-works reports)0 KRWConfirmed
Notice signs: installation and removal0 KRWConfirmed
Preparing the environmental cost use plan0 KRWConfirmed
Urgent pollution-control facilities (client-approved)0 KRWUnconfirmed
Confirmed / unconfirmed / rejected0 KRW / 0 KRW / 0 KRWConfirmed under Guideline Art 10(2)

Indirect settlement

Contract indirect amount
Unknown / pending
Expected reduction range
Unknown / pending
Overrun range (not paid automatically)
Unknown / pending

Use plan and additions

Use plan delay
Dates not entered
Added or changed items
0 KRW
Addition request candidate (added + maximum overrun)
Unknown / pending

Pending items and further checks

  • Enter a valid reference date from 2026-01-01 to 2026-12-31. Results stay pending without it.
  • This tool does not judge direct unit prices, whether facilities are legally required (dust-generating business or specified-works reports) or special contract terms.
Next-action checklist

Official rules checked: 2026-10-25 · Construction Technology Promotion Rule MST286885 (2026-06-11) Art 61 and Annex 8 (2021-08-27) · Environmental cost guideline notice 2018-528 · Construction Waste Decree Art 11 100 t

Related calculators

Why misreading the environmental budget costs money at completion

When a small Korean contractor wins a public works contract, the expense lines of the breakdown list the occupational safety and health budget, the quality-control cost, the environmental conservation cost and the waste disposal cost side by side.
Because the names look alike, contractors often hesitate over where dust nets, wheel-wash bays or temporary fences belong, and the same item ends up in two lines or in none.
The risk is that the indirect portion of the environmental conservation cost is settled by actual spending, so unsupported amounts are deducted at completion and overspending is not reimbursed automatically.

This construction environmental budget calculator applies the minimum rates by work type in Annex 8 of the Enforcement Rule of the Construction Technology Promotion Act to find the minimum indirect amount and checks whether the contract allocation falls short.
It separates the four direct facility groups, the indirect amount and the waste disposal cost into a total environmental management budget, and collects separately procured waste duplicates, double counting in other lines and main-purpose reclassification in one review.
Finally, it sorts indirect spending into confirmed, unconfirmed and rejected and shows the settlement reduction and overrun ranges.

Scope

This calculator is based on Korean rules checked on 2026-10-25 through the National Law Information OPEN API of the Ministry of Government Legislation.
It accepts reference dates from 2026-01-01 to 2026-12-31, and Annex 8 has not changed since its 2021-08-27 amendment.
The result is an arithmetic cross-check, not a client settlement approval, contract change or price adjustment decision.

Environmental management cost = conservation cost + waste disposal cost

Article 66(3) of the Construction Technology Promotion Act obliges the client to include in the contract price the environmental management cost needed to prevent environmental damage and pollution.
Rule Article 61(1) defines that cost as the cost of installing and running pollution-control facilities on site plus the cost of treating and recycling site waste, and Article 3 of the MOLIT guideline calls the first part the environmental conservation cost and the second the waste disposal cost.

Direct conservation cost

Depreciation, utility charges, materials and labor for installing, operating and removing control facilities.
It sits in direct expenses and is priced with market unit prices, standard estimates or quotes.

Indirect conservation cost

Testing, inspections, education and training, permits, notice signs and preparing the use plan.
It must be at least direct cost × the minimum rate and is settled by actual spending.

Waste disposal cost

On-site sorting, transport and loading, collection, storage, intermediate and final treatment by licensed firms, and on-site recycling.
Article 38 of the government pricing rule places it in direct expenses.

Article 39(2) of the contract pricing rule lists the occupational safety and health budget (item 7) and the environmental conservation cost (item 8) as separate indirect cost lines.
The two lines have different legal bases, rates and settlement methods, so one item must never be priced in both.

Minimum indirect environmental rates by work type (Rule Annex 8)

Annex 8 item 1(a) requires the indirect environmental amount to be at least the direct construction cost multiplied by the minimum rates below.
Annex 3 of MOLIT notice 2018-528 carries the same table.
The last column shows the minimum amount for a direct construction cost of KRW 3 billion.

Rule Annex 8 minimum indirect environmental rates by work type with a KRW 3 billion direct cost example
GroupWork typeMinimum rateMinimum at KRW 3 billion direct cost (KRW)
CivilRoad0.9%27,000,000
CivilPlant0.4%12,000,000
CivilSubway0.5%15,000,000
CivilRailway1.5%45,000,000
CivilWater supply and sewerage0.5%15,000,000
CivilHarbor (with a silt curtain or dredged-soil barrier)0.8% (1.8%)24,000,000 (54,000,000)
CivilDam1.1%33,000,000
CivilHousing-site development0.6%18,000,000
CivilOther civil works0.8%24,000,000
BuildingHousing (redevelopment and reconstruction)0.7%21,000,000
BuildingHousing (new build)0.3%9,000,000
BuildingOther building works0.5%15,000,000

Reading the rate table

  • The rate is an “at least” floor, so the calculator rounds sub-won fractions up
  • With two work types on one site, the type with the larger work amount applies (Guideline Article 6(3))
  • Separately procured contracts are calculated one by one with their own work types
  • Harbor works use 1.8% when a silt curtain or dredged-soil barrier is installed
  • There is no fixed minimum amount, and the direct portion follows its unit-price build-up

The four pollution-control facility groups in direct costs

Annex 8 item 1(b) and Guideline Article 5(1) divide on-site pollution-control facilities into four groups and name the environmental law each group serves.
The calculator’s four direct inputs follow this split, so divide lump-sum items in the breakdown along these lines.

Dust control

Wheel-wash facilities (including paving and sediment storage), sprinklers and water trucks, dust covers (including cut and fill slopes), dust walls, nets and screens, vacuum cleaners, dust collectors and mechanical sweepers.
They serve the Clean Air Conservation Act.

Noise and vibration control

Noise barriers (including moving and installation), sound sheets, silencers, noise covers and tunnels, noise forests and berms, sound absorbers, elastic supports, vibration dampers and trenches, rubber mounts and pipe isolators.
They serve the Noise and Vibration Control Act.

Waste facilities

Incinerators, chutes, scrap bins, waste storage with covers and drains, and construction-waste plants including crushing and dewatering.
These are facility costs and differ from the outsourced waste disposal cost.

Water pollution control

Wastewater treatment (including automatic monitoring), temporary drains and ditches, plastic covers on slopes, settling and coagulation facilities, silt curtains, oil booms, emulsifiers and absorbent pads, septic tanks and portable toilets with tanks.
They serve the water environment, groundwater, sewerage and chemical control laws.

Depreciation formula (Guideline Annex 2)

Depreciation = (depreciation rate + repair rate) × equipment price × operating hours ÷ (standard annual operating hours × service life)

Unless the standard estimates set otherwise, standard annual operating hours are 1,000, and service life is 5 years for machinery and 3 years for glass and metal items.
Utility charges follow government-announced rates, materials follow certified price surveys and labor follows the wage rates published by the construction and engineering associations.

Settling the indirect environmental amount by actual spending

Rule Article 61(2) settles the indirect portion of costs confirmed by the client or the construction manager according to actual spending.
Guideline Article 10(2) requires the contractor to have the quantities and costs of indirect spending confirmed at progress or completion inspection, so unsupported amounts drop out of the recognized total.

Settlement reduction range

Minimum reduction = max(0, contract − confirmed − unconfirmed)

Maximum reduction = max(0, contract − confirmed)

If every unconfirmed item is accepted you get the minimum, and if none is you get the maximum.
Rejected amounts are excluded from the start.

Overrun range

Overrun = max(0, recognized spending − contract amount)

The overrun is not paid automatically at settlement.
Under Guideline Article 9 the contractor requests an addition after consultation, and the client fixes it by contract change.

Urgent facilities need client approval first

The proviso to Guideline Article 6(2) lets urgent pollution-control facilities be settled from the indirect amount when the client accepts the need, for example to prevent imminent environmental damage.
Without an approval letter or minutes the cost may be rejected at settlement, so the calculator keeps this line separate and flags it.

Separate waste costs and the 100-tonne separate procurement rule

Annex 8 item 2 defines the waste treatment and recycling cost as on-site sorting, transport and loading, collection, storage, intermediate and final treatment by licensed firms, and on-site recycling, estimated from surveys of structures to be demolished or from design documents.
Item 2(c) states that when disposal is procured separately under Article 15 of the Construction Waste Recycling Act, that disposal cost is excluded from the works environmental budget.

Duty to procure construction-waste disposal separately by client type and outsourced tonnage
ClientOutsourced construction wasteSeparate procurementBasis
State, local government, public institutions, local public enterprises100 t or moreRequiredAct Article 15(1), Decree Article 11
State, local government, public institutions, local public enterprisesUnder 100 tNot requiredDecree Article 11
Private clientAny amountNo statutory duty (check the contract)Outside Article 15(1)
Any clientUnder 5 tOutside the definition; check the classAct Article 2(1)

If disposal is procured separately but the works contract still prices construction-waste disposal, the same tonnage is paid twice.
When separate procurement is “Yes”, the calculator shows the whole construction-waste disposal amount in the works contract as a duplicate, and when a public client has 100 tonnes or more but the answer is “No”, it warns that separation is missing.
Designated waste such as asbestos and business waste are outside separate procurement, so they have their own input.

Telling it apart from the safety and health budget and quality cost

Most disputes arise when one item serves both environmental and safety purposes.
Guideline Article 5(2) says that even an item on the pollution-control list belongs to the line matching its main purpose when that purpose is site operation, smooth progress or worker safety and health.

Comparison of the environmental conservation cost, waste disposal cost, safety and health budget and quality-control cost
Cost lineLegal basisAllocationSettlement
Environmental conservationConstruction Technology Promotion Act Article 66, Rule Article 61 and Annex 8Direct unit prices + indirect at least direct cost × the Annex 8 minimum rateIndirect portion by actual spending
Waste disposalAnnex 8 item 2, Construction Waste Recycling Act Article 15Tonnage × treatment price, excluded if procured separatelyContract change when quantities move
Occupational safety and health budgetOccupational Safety and Health Act, Ministry of Employment and Labor noticeBase amount × rate by work typeSpending review with item caps
Quality controlConstruction Technology Promotion Rule Annex 6Testing and inspection costsSettled by test records

Common boundary cases

  • Decide the main purpose first: a fall-protection net belongs to the safety budget, while a dust net that blocks fugitive dust belongs to the environmental cost
  • A temporary fence for access control usually serves site operation and is often a temporary-works item
  • Toilets for worker hygiene and portable toilets with tanks for water-pollution control are told apart by the purpose written in the design
  • Check from the report type whether a measurement fee is a quality test or an environmental measurement

Two fictional examples of the calculation

The example buttons load the two fictional projects below.
They are not figures from real design documents and only show how the calculation flows.

Environmental budget results for the fictional public welfare center and road plus sewer composite examples
ItemWelfare center (0.5%)Road + sewer (0.9%)
Direct construction cost3,200,000,0002,900,000,000
Minimum indirect amount16,000,00026,100,000
Contract indirect amount / shortfall14,500,000 / 1,500,00026,100,000 / 0
Four direct groups36,000,00071,000,000
Waste disposal total7,700,00047,000,000
Environmental management total58,200,000144,100,000
Duplicates and reclassification1,800,00041,000,000
Indirect settlement reduction range3,700,000 ~ 6,800,0000 ~ 8,500,000
Overrun range / addition candidate0 / 00 ~ 3,500,000 / 8,500,000

What the welfare center shows

Other building works at 0.5% of KRW 3.2 billion gives a minimum of KRW 16,000,000, but the contract has KRW 14,500,000, so KRW 1,500,000 is short.
Confirmed spending of KRW 7,700,000 plus KRW 3,100,000 unconfirmed leaves a reduction between KRW 3,700,000 and KRW 6,800,000.

What the composite works show

Road works of KRW 4.0 billion outweigh sewer works of KRW 0.9 billion, so road 0.9% applies and the KRW 26,100,000 minimum matches the contract.
The works contract still prices KRW 38,000,000 of disposal on top of the separately procured 650-tonne service, so the duplicate grows, and the use plan was submitted 5 days after the first facility was installed.

Use plan submission, revisions and additions

Many environmental budget disputes start with procedure rather than amounts.
Rule Article 61(2) and Guideline Article 8 require the use plan to reach the client before the first pollution-control facility is installed, and a revised plan before any change is carried out.

  1. Right after starting, prepare the use (revision) plan (Form 1) and the detailed use plan (Form 2) and submit them before the first facility is installed
  2. Attach unit-price and quantity sheets for lump-sum items under Guideline Article 6(4)
  3. When facilities are added, lump sums change or waste rises, submit a revised plan before carrying it out and discuss an addition with the client and construction manager
  4. At progress or completion inspection, have indirect quantities and costs confirmed and keep photos, test reports and tax invoices together
  5. Put the reduction and overrun ranges into the review and use it for reduction talks or a contract-change request

Step-by-step use and practical scenarios

  1. Choose the reference date, client type and work type, and for composite works add work type 2 and both work amounts
  2. Enter the direct construction cost, the four direct groups, the indirect amount and the three waste lines from the cost statement
  3. Add the outsourced tonnage, the separate procurement answer and any reclassified or double-counted amounts
  4. Enter the seven indirect spending rows with their status and compare the plan submission and first installation dates
  5. Save or print the TXT review and send it with the checklist to the client and construction manager

Reviewing the breakdown after award

If the indirect amount is below the minimum rate, asking for a cost-statement check early in the works is far easier than just before completion.
The rate moves from 0.3% to 1.5% with the work type, so confirm the work type basis in the design as well.

Checking evidence before completion

The more unconfirmed spending you have, the wider the reduction range.
Collecting test reports, training logs, permit receipts and sign photos by line to turn unconfirmed items into confirmed ones is the surest way to reduce deductions.

Tips and cautions

  • Enter amounts excluding VAT so they match the cost statement
  • Follow the client’s cost statement on whether owner-supplied materials are in direct cost
  • Environmental costs spent in subcontracted work are easier to confirm when they are reflected in the main contractor’s plan and settlement evidence
  • Use the memo for the design document, date and officer; amounts and memos are not sent as analytics events

Frequently asked questions

Are the environmental conservation cost and the environmental management cost the same thing?

No.
The environmental management cost in Article 66(3) of the Construction Technology Promotion Act is the umbrella term, and Article 3 of the MOLIT guideline splits it into the environmental conservation cost and the waste disposal cost.
Conservation covers installing and running dust, noise and vibration, waste-facility and water-pollution controls.
Waste disposal covers on-site sorting, transport, outsourced treatment and recycling.
Check the two amounts separately in the contract breakdown.

What is the minimum indirect rate multiplied by?

Rule Annex 8 requires the environmental amount in indirect costs to be at least the direct construction cost multiplied by the minimum rate for the work type.
Direct construction cost is materials plus direct labor plus direct expenses in the cost statement.
Multiplying the total project cost or the contract price overstates the minimum, so enter the direct construction cost from the client’s cost statement.

Is there a minimum for the direct portion of the environmental cost?

There is no fixed minimum.
Guideline Article 6(2) has the direct portion built from depreciation, utility charges, materials and labor for installing, operating and removing facilities, priced with market unit prices, standard estimates or quotes.
The calculator therefore shows the direct portion only as a total and a share, and applies the minimum test only to the indirect portion.

What happens if the indirect environmental amount is not fully spent?

Rule Article 61(2) settles the indirect portion of costs confirmed by the client or the construction manager according to actual spending.
If confirmed spending is below the contract amount, the difference can be deducted at progress or completion settlement.
The calculator keeps unconfirmed spending as a range and shows the minimum and maximum reduction.

If spending exceeds the contract amount, is the difference paid?

Not automatically.
Annex 8 item 3 and Guideline Article 9 allow the contractor to request an addition after consulting the client and the construction manager when facilities are added, lump-sum contents change or waste quantities rise.
The amount changes only after the client confirms it and makes a contract change, so use the overrun range only as support for that request.

Is a dust net or a temporary fence an environmental cost or a safety cost?

Guideline Article 5(2) says that even an item on the pollution-control list belongs to the line matching its main purpose when that purpose is site operation, smooth progress of the works or worker safety and health.
Putting the same item in both the safety and health budget and the environmental cost is double counting.
Confirm the main purpose and the design item and keep it in one line only.

Must private projects procure construction-waste disposal separately?

The separation duty in Article 15(1) of the Construction Waste Recycling Act applies to the state, local governments and the bodies listed in Article 2(15), such as public institutions, local public enterprises and private-investment concessionaires.
Decree Article 11 sets the threshold at 100 tonnes or more of construction waste sent for outside disposal.
Private clients have no statutory duty, but a contract may still require separation, so check the contract.

Can I submit the result as my settlement claim?

The result is an arithmetic cross-check of the amounts you entered.
It does not judge direct unit prices, whether facilities are legally required, whether the client will accept the spending, contract-change approval or special contract terms.
Send the review with the use plan, the detailed plan and the unit-price sheets, and get confirmation from the client and the construction manager.

Official sources, update policy and next steps

Statutes and administrative rules were searched and their articles and annex texts checked directly through the National Law Information OPEN API.
The Construction Technology Promotion Act MST276921 (effective 2025-10-01), its Decree MST286847 (effective 2026-06-09) and its Enforcement Rule MST286885 (effective 2026-06-11) are all current, and Annex 8 is the 2021-08-27 amendment.
The guideline is MOLIT notice 2018-528 (effective 2019-01-01, administrative rule serial 2100000149175), and the Construction Waste Recycling Act MST276695 and its Decree MST278497 are the versions effective 2025-10-01.

Rates and thresholds are rechecked immediately when Annex 8, the guideline (reviewed every three years) or the waste decree changes, and otherwise once a year.
Special contract terms and agency guidance may prevail for an individual project, so confirm the latest basis with the client before filing a settlement claim.
Enter your contract breakdown now to find indirect shortfalls and double counting, and save the review for settlement and addition discussions.