NDT Weld Scope, Inspection Rate & Site Quote Calculator

Check approved weld lengths or counts, visit costs and a separate retest budget using actual quotes in KRW.

Enter an approved inspection plan and actual quote. All amounts are KRW.

1. Weld list and inspection scope

Each row is a separate approved scope. A count percentage is not a length percentage. Recheck the population unit whenever changing modes.

Complete visit costs to confirm the total. Enter 0 when no separate charge applies.

3. Separate tax and retest scenario

Inspection scope and order budget

Enter the first group’s population to see its inspection quantity.

Use methods, percentages and selections confirmed under the applicable specification by the client and inspection provider. Length and weld counts are never converted or combined.

Confirm with the inspection provider

Related calculators

Build an NDT quote from a confirmed weld scope

An inspection percentage needs a denominator: total weld length and number of weld locations produce different quantities.
A quote may also exclude preparation, equipment, inspector person-days or travel.
This calculator turns an inspection plan confirmed by your client and inspection provider into a quantity and cost ledger.
Use it to reconcile the scope and request a written quotation before ordering.

It does not select inspection methods, choose welds, predict acceptance or determine a statutory percentage.
All monetary inputs and outputs use KRW, including this English page.
Enter actual contract prices; leave unconfirmed amounts blank and enter zero only when no separate charge has been confirmed.

Prepare the weld list and inspection documents

  • Weld identifiers, drawing references, revisions and the approved inspection-plan version
  • Method, population length or count, percentage denominator and selection basis for each group
  • Written partial-inspection permissions, minimum actual inspection quantity and length-rounding increment
  • Actual inspection prices and the inclusion schedule for preparation, equipment, person-days and travel
  • Confirmed reinspection scope, extra callout conditions, separately charged tax and quote validity

Create groups with non-overlapping scopes and the same method and billing basis.
Include weld identifiers or drawing references in the group label so the aggregate can be traced back to the source list.
The approved locations remain in your external inspection documents: entering an aggregate here does not approve positions, sequence or a procedure.

RT, UT, MT and PT identify the quoted method

RT and UT

RT uses radiation; UT uses ultrasonic sound waves.
Keep their scopes separate even when the entered percentages match.
An appropriately qualified specialist must confirm suitability for the material, geometry, expected discontinuities, access and applicable specification.

MT and PT

Magnetic particle testing, MT, addresses surface and near-surface discontinuities in ferromagnetic materials.
Liquid penetrant testing, PT, addresses surface-opening discontinuities.
Choosing a label here does not establish material suitability, detection performance, surface preparation or acceptance.

Choose length, count or approved-list mode

Length mode applies the percentage to the confirmed total weld length in metres.
Count mode applies it to the number of weld locations and rounds up to a whole location.
Two selected welds do not necessarily represent the same percentage of total length, especially when weld lengths differ or partial inspection is permitted.
The calculator therefore never converts a count percentage into inspected length.

For a count-based plan billed by length, obtain the actual inspected length of the approved selection and enter that aggregate in approved-list mode.
This mode takes the confirmed length or count directly, without applying percentage, minimum or increment again.
Check that a listed weld’s full length has not been confused with its approved partial-inspection length.
When switching modes, recheck the population label and unit; a preserved number is not automatically a valid new denominator.

Apply contractual rounding and minimum quantities

Length quantity = ceil(max(population × percentage / 100, minimum) / increment) × increment

Count quantity = max(ceil(population × percentage / 100), minimum)

Approved-list quantity = confirmed selected aggregate

The minimum means actual inspection quantity, not a minimum invoice or callout charge.
Do not place a monetary billing floor in this field.
If rounding or the minimum produces more inspection quantity than the population, the result is withheld instead of silently capped.
Ask the provider to resolve the population, unit or contract-condition conflict before using the result.

Separate preparation, equipment, labour and travel

Each inspection group costs its quantity multiplied by the actual unit price.
A visit adds preparation, equipment-days multiplied by the equipment rate, person-days multiplied by the labour rate, and travel expenses.
Allocate surface preparation according to the actual contract and avoid charging it again if already included.
Confirm how the provider calculates person-days, including multiple inspectors, short visits, waiting and overtime.

Shared equipment used for several groups can be recorded once in the visit ledger rather than repeated against every group.
Confirm night work, restricted-area arrangements, waiting and additional movements separately.
Enter the actual separately charged tax amount: the calculator applies no default tax rate.
If prices already include tax, confirm that no extra tax is due before entering zero.

Worked example: a KRW 590,000 base order

  • UT: 101.2m × 10% = 10.12m; round upward in 0.5m increments to 10.5m; 10.5 × KRW 20,000 = KRW 210,000
  • MT: 11 weld locations × 10% = 1.1; round up to 2 locations; 2 × KRW 30,000 = KRW 60,000
  • Visit: KRW 50,000 preparation + 1 equipment-day × KRW 80,000 + 1 person-day × KRW 150,000 + KRW 40,000 travel = KRW 320,000
  • With separately charged tax confirmed as KRW 0: 210,000 + 60,000 + 320,000 = KRW 590,000

All example prices and percentages are fictional calculation inputs, not market prices or standard inspection requirements.
Read the quantities separately as UT 10.5m and MT 2 weld locations.
Adding different methods and units into one quantity would obscure the actual order scope.
Replace both the numbers and the inclusion conditions before applying the example to a real contract.

Keep reinspection as a separate scenario

Reinspection is not predicted from a defect percentage.
Enter a confirmed scenario quantity, actual reinspection rate, extra visit cost and separately charged tax.
The model covers one reinspection scenario within the original population, without automatically repeating repair and inspection cycles.
A confirmed zero reinspection quantity needs no price to establish a zero inspection charge for that group.

In the fictional example, UT reinspection is 1m × KRW 20,000, MT reinspection is 0 locations, the extra visit costs KRW 40,000 and extra tax is KRW 0.
The scenario adds KRW 60,000 to the KRW 590,000 base, giving KRW 650,000 including reinspection.
This is the budget if the entered scope occurs, not an expected loss or a probability of defects.

Read blanks, zero and known subtotals correctly

A blank means unconfirmed, not free.
Known quantities can support a price enquiry before every charge is available.
The known subtotal adds the currently valid confirmed components; it is not a guaranteed contractual floor.
When the final total is withheld, obtain the missing charges and reconcile the inclusion schedule before committing an order.

Negative values, out-of-range entries and fractional weld counts need correction.
Length and percentage accept up to three decimal places; monetary inputs are whole KRW.
Line amounts are rounded to whole KRW before summing.
Amounts exceeding safe integer precision are withheld.
Input limits are software precision boundaries, not engineering or safety capacities.

Use the ledger to request a matching written quote

  1. Create non-overlapping groups from the approved drawing and weld list; confirm method and denominator.
  2. Enter percentage, minimum and increment, or the approved-list aggregate; check the quantities.
  3. Add inspection prices, visit charges and actual extra tax; check for duplicate included work.
  4. If needed, enter the separate reinspection scenario and compare its extra cost with the base order.
  5. Review plan, scope, billing-unit and schedule/extra-charge checks, then save the TXT report or print it for reconciliation.

During fabrication, avoid mixing quantities from different drawing revisions.
During maintenance, confirm access windows and visit counts because a change can alter callout costs.
Saving or sending a report does not book an inspection or create a contract.
Request the provider’s written confirmation of the same scope and schedule before placing an order.

Frequently asked questions

Does the calculator choose an inspection percentage?

No. Use the percentage in the applicable specification and the plan confirmed by the client and inspection provider.
The example is not a statutory percentage.

Can a count result be used for a length-based quote?

Obtain the actual inspected length of the approved selected welds first.
Different weld lengths and partial inspection prevent automatic conversion.
Enter that confirmed length in approved-list mode.

Is a minimum callout charge a minimum inspection quantity?

No. The quantity field describes actual inspection scope.
Confirm the monetary charging structure with the provider and allocate the visit charge without replacing a quantity with money.

What if the result exceeds the population?

Reconcile the minimum, rounding increment and denominator.
The calculator withholds the conflict instead of reducing the contractual target silently.
Correct the source plan or agreed condition and recalculate.

Is the reinspection extra an expected defect cost?

It is a conditional budget for the entered scope.
No acceptance or defect probability is calculated.
Also confirm whether physical repair work is included in the inspection contract.

Does the English page use different rules?

It uses the same quantity formulas and KRW amounts.
Korean legislation is described only in its Korean jurisdictional context and does not replace another country’s rules or project specification.

Primary sources and update context

Sources checked on 2026-11-25.
For Korea, the Act on the Promotion and Management of Non-Destructive Testing Technology, effective 2022-04-21, provides the definition in article 2 and business-registration context in article 11.
Article 2 of its Enforcement Decree, effective 2026-02-01, lists inspection methods.
These provisions are not adopted as a project-specific percentage or price.
Ask the inspection provider about separate sector rules, applicable specifications and your actual contract.

Reconfirm prices, units, approved selections, equipment/person-day billing, travel and tax inclusions for every order.
Refresh the plan revision and quantities when drawings change.
Review source links at least every six months.
The ledger is not a safety approval or an inspection certificate.

Reconcile scope and cost in one order ledger

Start with the first group’s identifier and population.
Once the quantity is checked, add actual prices and visit costs, then fill missing items from the provider’s reply.
Save the base and reinspection budgets alongside the approved selection, selection basis and visit schedule to obtain a matching written quotation.